Dosage & consumption

Grinding Aid Dosage Calculator

Published by CementGrindingAid.com · Last reviewed 10 October 2026 · How this content is produced

Use plant throughput and a trial dosage to plan pump settings, stock requirements and trial quantities.

Enter your operating data

Enter values and calculate.

Inputs remain in your browser; this page does not submit them.

Method questions

Frequently asked questions

How do I convert g/t to percent?

Divide g/t by 10,000. For example, 300 g/t equals 0.03% by cement mass.

Does the result include product density?

No. Results are mass-based. Convert kg/h to L/h using the current product density.

Can I use nameplate mill capacity?

Use actual stable throughput for operating estimates; nameplate capacity can overstate consumption.

Next engineering step

From calculation to mill trial

Calculation results are not submitted automatically. Send the selected product, assumptions and mill baseline to Tony when requesting a technical review.

Check the result against a transparent example

At 100 t/h, a user-selected 300 g/t, 20 h/day and 25 days/month, the mass results are 30 kg/h, 600 kg/day and 15,000 kg/month (15 t/month as displayed by this calculator). These inputs illustrate arithmetic only; they are not a dosage recommendation.

Before using the quantity in an enquiry

  • Specify whether the chosen dose is supplied-product or active-solids based.
  • Confirm the treated material basis and whether hours and days are planned or measured.
  • For L/h, divide kg/h by the grade-specific density in kg/L. This calculator does not perform that conversion.
  • Review performance separately: consumption calculations cannot establish quality, savings or suitability.

Read the unit and density example → Save a trial review record → Review the named product.